CAVE NETWORK – Altamura (BA)
Thumbnail 1
Thumbnail 1
Thumbnail 2
Thumbnail 3
Thumbnail 4
Thumbnail 5
Thumbnail 6
Thumbnail 7
previous arrow
next arrow
Thumbnail 1
Thumbnail 1
Thumbnail 2
Thumbnail 3
Thumbnail 4
Thumbnail 5
Thumbnail 6
Thumbnail 7
previous arrow
next arrow
SITE MANAGER

Ing. Vito VERNI

IMPLEMENTING AGENCY

COMMISSARIO STRAORDINARIO DELEGATO "per l'attuazione degli interventi per la mitigazione del rischio idrogeologico nella Regione Puglia previsti nell'Accordo di Programma siglato il 25.11.2010"

PROJECT DESCRIPTION

Hydrogeological risk mitigation intervention connected to the presence of a caveal network of anthropogenic origin in the Municipality of Altamura (BA)

HEAD PROJECT MANAGER

Geom. Vincenzo MARTIMUCCI

PROJECT

-

PROJECT DURATION

23/10/2015 - 07/02/2017

TOTAL COST

€ 1.804.035,79

PROJECT SPECIFICATIONS

The risk containment interventions within this project consist in the restoration of the caves by filling them with concrete. Namely, four types of intervention have been planned:

– for accessible caves, construction of partition barriers and filling the cave with a cement mix;

– for caves deemed not accessible because of collapses, the possibility of concrete filling will be considered after the results of accurate feasibility studies beyond the collapsed section;

– for deeper caves, inaccessible due to collapses, sizeable amounts of concrete will be poured from above;

 – for areas in which geognostic surveys (sound,

[...]Read More

The risk containment interventions within this project consist in the restoration of the caves by filling them with concrete. Namely, four types of intervention have been planned:

– for accessible caves, construction of partition barriers and filling the cave with a cement mix;

– for caves deemed not accessible because of collapses, the possibility of concrete filling will be considered after the results of accurate feasibility studies beyond the collapsed section;

– for deeper caves, inaccessible due to collapses, sizeable amounts of concrete will be poured from above;

 – for areas in which geognostic surveys (sound, electrical and seismic tomography) have detected uneven material and/or anomalies correlated to the presence of caves, an additional survey will be carried out to verify the actual presence of caves and their condition. Additional surveys of this type are also planned in areas where the inspected caves are entirely filled with sand/silt deposits. The restoration of the interested hypogeal caves is a continuation of the first safety interventions started by the municipal administration in the “Chiancone-Fornaci” area, on Via Copenhagen and on the southern part of Via Parigi, along with interventions on via Barcellona.

Read Less

RELATED NEWS

4 May 2023

Cobar al Salone Internazionale del Restauro di Ferrara

Dal 10 al 12 maggio saremo presenti con un nostro stand espositivo al Salone Internazionale del Restauro di Ferrara.

Anche quest’anno parteciperemo ad una manifestazione unica, un luogo d’incontro per aziende, istituzioni, ricercatori e appassionati del mondo del settore del restauro. Il successo di questi eventi contribuisce all’evoluzione del nostro lavoro e alla valorizzazione del patrimonio storico e culturale dell’Italia e siamo fieri di poter contribuire al suo successo, mostrando i risultati del nostro lavoro.